FPG field guide
Use this checklist before a cladding or building-envelope shop-drawing package starts. It helps the project team identify the governing set, unresolved interfaces and review responsibilities without inventing missing dimensions.
1. Lock the governing source set
- Current architectural drawing set, sheet index, issue date and revision.
- Building-envelope details, wall types and consultant narratives.
- Structural drawings and approved attachment or support criteria.
- Project specifications, addenda, bulletins and issued clarifications.
- Window, door, louvre and penetration schedules from the responsible supplier.
- Approved product data and current manufacturer installation instructions for every selected system.
- Approved substitutions and written consultant responses affecting the cladding assembly.
- Verified field surveys, only where existing construction or as-built conditions govern.
Mark superseded material clearly. If two documents conflict, record the conflict as an RFI instead of choosing a dimension or requirement.
2. Define the actual wall assembly
- Cladding product, material, thickness, finish, colour, orientation and approved lot constraints.
- Panel or plank system, joint type, reveal width and installation direction.
- Substrate, sheathing, air/water or air/vapour barrier and transition membranes.
- Exterior insulation type and thickness.
- Thermal clips, girts, rails, subframing and attachment direction.
- Rainscreen cavity depth, drainage, ventilation and required insect screens.
- Fastener type, material, spacing and substrate capacity, when supplied by the responsible designer.
- Fire-stopping, cavity barriers and other life-safety requirements identified by the project documents.
3. Confirm geometry before detailing
- Grids, levels, control lines and benchmark information.
- Facade extents, module intent and panel-joint alignment.
- Opening sizes and locations tied to the current window and door schedules.
- Parapet, soffit, balcony, foundation and base-of-wall elevations.
- Required slopes, clearances and drainage paths.
- Existing-condition measurements recorded with date, location, method and reviewer.
Unverified field dimensions stay on hold. A photograph without a scale or a dimension without a traceable source is not a fabrication input.
4. Inventory every interface and transition
Openings
Head, jamb and sill flashings; membrane continuity; end dams; drips; weeps; sealant joints; window and door supplier tolerances.
Edges
Inside and outside corners, terminations, exposed ends, returns, closures and finish boundaries.
Horizontal conditions
Base of wall, foundation, floor lines, shelf angles, balconies, canopies, parapets and soffits.
Mixed systems
ACM-to-fibre-cement, metal-to-stone, panel-to-glazing and other selected system transitions.
Penetrations
Louvres, vents, pipes, lights, signs, conduits, anchors and exterior equipment supports.
Fabrication
Flashing gauge, material, finish, slopes, hems, end dams, drips, weeps, developed widths and bend sequence—only when verified.
5. Confirm the review and approval path
- Identify who owns architectural intent, envelope performance, structural attachment and fabrication approval.
- Identify whether delegated design, sealed calculations or professional review are required.
- List submission recipients, review periods and the meaning of each approval status.
- Assign every hold and RFI to a responsible party and due date.
- Record consultant comments against the exact sheet and revision they reviewed.
- Do not release superseded or unapproved details for fabrication.
6. Agree the package deliverables
- Cover sheet, source register and revision record.
- Reference plans and elevations with controlled panel or plank layouts.
- Wall sections and assembly references.
- Window and door head, jamb and sill details.
- Base, corner, parapet, soffit and mixed-system transition details.
- Flashing profiles and fabrication tickets where the required inputs are verified.
- Schedules for materials, finishes, details, holds and RFIs.
- Issue status, approval record and superseded-sheet controls.
Primary references to confirm for each project
- Province of British Columbia — BC Building Code 2024
- City of Vancouver — current Vancouver Building By-law
- BC Housing — Building Envelope Guide for Houses
- ALPOLIC — current fabrication manuals
- ALUCOBOND — system and fabrication details
- Longboard — exterior installation guides
- James Hardie Canada — current technical documents
These links establish source categories, not project approval. Always use the exact product, jurisdiction, permit date and revision applicable to the project.
Start a controlled shop-drawing intake or review the ACM and rainscreen coordination guide.