Air & Vapour Barriers

A clear view of substrate, continuity and transitions, with project-specific inspection requirements.

01 / 04

Substrate

Review the substrate and the project requirements before the sequence is agreed.

02 / 04

Continuity

Coordinate laps and continuity with the selected barrier system.

03 / 04

Transitions

Review penetrations and transitions against the specified project details.

04 / 04

Inspection

Keep the project inspection requirements and review responsibilities visible.

Read the sequence and scope
  1. Substrate. Review the substrate and the project requirements before the sequence is agreed.
  2. Continuity. Coordinate laps and continuity with the selected barrier system.
  3. Transitions. Review penetrations and transitions against the specified project details.
  4. Inspection. Keep the project inspection requirements and review responsibilities visible.

Presentation only. Follow the specified project documents, selected system requirements and agreed review responsibilities. The reference geometry is illustrative and not to scale. Existing service limitations and technical notes remain below.

Further service context and original reference images
BUILDING ENVELOPE · AVB

Continuous air and vapour barriers — self-adhered membranes and fluid-applied coatings, detailed at every transition and inspected.

Air & Vapour Barriers
MEMBRANES
Self-adhered + fluid
BRANDS
Henry · Blueskin · Soprema · Prosoco
QA
Pre-install mockups
WARRANTY
Manufacturer-backed

Scope

How we install AVB

Continuous, sealed, inspected — from sheathing to parapet — by trained envelope crews.

  • Self-adhered sheet membranes (Blueskin VP100, Soprema)
  • Fluid-applied AVB (Henry Air-Bloc, Prosoco R-Guard)
  • Window perimeter, deck-to-wall + parapet detailing
  • Compatible primers, transition strips and sealants
  • Pre-install mockups and field QA inspection

Need AVB scope handled?

Send the spec section — we’ll price installation, mockup and field QA.

Air / water-resistive barrier — animated installation sequence

Project-specific reference details and governing notes
Air and water-resistive barrier on exterior sheathing — installation sequence, generic system, not to scaleCabinet-oblique cutaway of one wall bay that turns a true outside corner on the left and a true inside corner on the right. Layers in build order: steel stud frame and tracks, exterior sheathing with a window rough opening and a pipe penetration, surface preparation and primer, sheathing joint strips and reinforced corner pre-strips, base through-wall flashing with the transition membrane lapped over the upstand, self-adhered sheet courses laid bottom-up with staggered end laps, an interleaved penetration collar, a membrane sill pan with back dam and end upturns, jamb and head strips followed by the held closing course, a mechanical top termination with a sealant bead, a fluid-applied alternate, and a continuous airtightness line with three outward drainage paths. Head, jamb, sill pan, base, penetration, top termination and both corner plan sections are drawn as separate insets. Every dimension is a visible HOLD; the drawing is generic and illustrative only. AIR / WATER-RESISTIVE BARRIER — INSTALLATION SEQUENCE Fig Philp Group Inc. · Motion V1 · generic self-adhered sheet barrier on exterior sheathing · fluid-applied alternate shown CABINET OBLIQUE, NTS, GENERIC ILLUSTRATIVE — no FPG Detail Library record applies to this system family; every quantity is a visible HOLD LAYER SEQUENCE HOLDS IN THIS VIEW — NO DIMENSION IS ASSERTED STEEL STUD FRAME + TRACKBOTTOM TRACKROUGH OPENINGPIPE PENETRATION01 SUBSTRATE + FRAMINGSHEATHING TYPE + FASTENING PER PROJECT DESIGN SUBSTRATE DRY / SOUND / DUST-FREE — PRIMED PER MANUFACTURER02 SURFACE PREP + PRIMERADHESION IS THE WHOLE ATTACHMENT METHOD OC PRE-STRIPIC PRE-STRIPJOINT STRIPS03 JOINTS + CORNER PRE-STRIPSDETAILED BEFORE ANY FIELD SHEET GOES ONOUTSIDE CORNER — TRUE PLANPLAN SECTION — NTSBOTH PLANES MEET AT A CONVEX ARRIS;THE MEMBRANE STACK TURNS THE CORNERPRE-STRIP, EQUAL LEGSFIELD OVER STRIPCORNER PRE-STRIP LEG LENGTH — HOLDCORNER PRE-STRIP WIDTH — HOLDINSIDE CORNER — TRUE PLANPLAN SECTION — NTSBOTH PLANES MEET AT A RE-ENTRANTJUNCTION; THE STACK IS CONTINUOUSSTRIP WORKED TIGHT — NO VOIDFIELD OVER STRIPCORNER PRE-STRIP LEG LENGTH — HOLDCORNER PRE-STRIP WIDTH — HOLD MEMBRANE OVER FLASHING UPSTAND — NEVER BEHINDHEMMED DRIP — DRY SIDE04 BASE THROUGH-WALL FLASHINGMEMBRANE OVER THE UPSTAND — NEVER BEHINDBASE TIE-IN — SECTIONSECTION — NTSTRANSITION MEMBRANE BONDS TO THESHEATHING AND LAPS OVER THE UPSTANDEND DAM AT EACH LENGTH ENDHEMMED DRIP TURNED TO THEDRY SIDE — NO WATER POCKETLENGTH-TO-LENGTH LAPS SHINGLED AND SEALED.NO LIBRARY PROFILE RECORD APPLIES.FLASHING PROFILE / UPSTAND / SLOPE — HOLDDRIP / END DAM / LENGTH LAP — HOLDHEIGHT ABOVE GRADE + TRANSITION LAP — HOLD RELEASE LINER PEELED AS THE SHEET IS SETROLLED AS IT LANDS05 FIRST COURSE (ROLLED)LAPPED DOWN OVER THE BASE TRANSITION STRIP END LAPS STAGGEREDSTOP — DETAIL FIRST06 COURSING UP TO PENETRATIONBOTTOM-UP; COURSING STOPS AT THE PIPE ABA COLLAR OVER FIELD BELOWB FIELD ABOVE OVER COLLAR07 PENETRATION COLLARINTERLEAVED — THE COUNTER-LAP IS REALPENETRATION — SECTIONSECTION — NTSTHE COLLAR IS INTERLEAVED INTO THECOURSING, NOT APPLIED OVER ITABCOLLAR OVER FIELD BELOWFIELD ABOVE OVER COLLARINSTALLED WHILE THE COURSING ABOVE IS OPEN;NOTHING HAS TO BE PEELED BACK LATER.COLLAR OVERLAP ONTO FIELD — HOLDCOLLAR OVERLAP ONTO PIPE — HOLDSEALANT FILLET SIZE — HOLD MEMBRANE RETURNED INTO THE REVEALSHELD — AFTER HEAD STRIP08 COURSING HELD AT HEAD LINENO FIELD SHEET CROSSES THE HEAD YET BACK DAM09 SILL PANDELIVERS WATER OUT OF THE OPENINGSILL PAN — SECTIONSECTION — NTSBACK DAM CONTINUOUS ALONG THEINTERIOR EDGE; ENDS UPTURNEDAPRON LAPPED OVERTHE COURSE BELOWPAN CORNERS FORMED OR PRE-FORMED —NO CUT THROUGH THE DRAINAGE PLANESILL PAN BACK DAM HEIGHT — HOLDSILL PAN END-UPTURN HEIGHT — HOLDSILL PAN SLOPE TO EXTERIOR — HOLD 1PAN2JAMB3HEAD4FIELDWINDOW SCOPE: SEE NOTE 210 JAMB, HEAD, CLOSING COURSEPAN, JAMB, HEAD, FIELD — IN THAT ORDERHEAD — SECTIONSECTION — NTSFIELD COURSE INSTALLED LAST —LAPS DOWN OVER THE HEAD STRIPFIELD COURSEHEAD STRIPHEAD STRIP OVER BOTH JAMB STRIPS, RETURNEDONTO THE FIELD · WINDOW SCOPE: SEE NOTE 2HEAD STRIP RETURN WIDTH — HOLDMEMBRANE RETURN DEPTH INTO REVEAL — HOLDJAMB — PLAN SECTIONPLAN SECTION — NTSJAMB STRIP RETURNS FROM THE REVEALONTO THE FIELD MEMBRANEJAMB STRIPFIELD MEMBRANE OVER STRIPLAPS OVER THE SILL-PAN END UPTURN;TOP END COVERED BY THE HEAD STRIPJAMB STRIP RETURN WIDTH — HOLDMEMBRANE RETURN DEPTH INTO REVEAL — HOLD TERMINATION BAR + SEALANT — NOTE 3ROLLER — ALL LAPS + FIELDFISHMOUTH CUT, LAID FLAT, PATCHED11 TOP TERMINATION + ROLLERMECHANICAL TERMINATION, NOT ADHESION ALONETOP TERMINATION — SECTIONSECTION — NTSMECHANICALLY TERMINATED AND SEALED —NOT LEFT TO ADHESION ALONESEALANT BEAD OVER BARWASHER-HEAD FASTENERMEMBRANE TOP EDGE CLAMPEDFASTENERS ILLUSTRATIVE ONLY — NOTE 3TOP TERMINATION HEIGHT — HOLDFASTENER TYPE / MATERIAL / SPACING — HOLDEMBEDMENT / EDGE DISTANCE / SEALANT — HOLD FLUID-APPLIED ALTERNATESAME AIRTIGHTNESS LINE — NTSSHEET SYSTEMFLUID + DETAIL FABRICWET-FILM GAUGE — READING BLANKWET-FILM / DRY-FILM / COATS — HOLDRECOAT + CURE TIME — HOLDDETAIL-FABRIC EMBEDMENT WIDTH — HOLD12 FLUID-APPLIED ALTERNATESELECTION PER PROJECT SPECIFICATION AIRTIGHTNESS LINE — CONTINUOUSNO PATH TURNS INWARDVAPOUR CLASS — PROJECT DESIGNVAPOUR-PERMEABLE (DRIES OUTWARD)VAPOUR BARRIER (VAPOUR-CLOSED)MEMBRANE PERMEANCE / CLASS — HOLD (NOTE 5)13 CONTINUITY — AIRTIGHTNESSEVERY DRAINAGE PATH EXITS OUTWARD FUTURE CLADDING LINEHEADJAMBSILL PANBASEPENTOP TERMOCIC14 COMPLETE ASSEMBLY — NTSAIRTIGHT FACE OF A FUTURE RAINSCREEN CAVITY STUD SPACING — HOLDSHEATHING THICKNESS — HOLDROUGH-OPENING SIZE + PIPE DIAMETER — HOLDPRIMER COVERAGE + OPEN / FLASH TIME — HOLDSUBSTRATE + AMBIENT APPLICATION TEMP — HOLDSHEATHING JOINT-STRIP WIDTH — HOLDMEMBRANE SHEET WIDTH / COURSE HEIGHT — HOLDHORIZONTAL LAP WIDTH — HOLDEND LAP WIDTH + STAGGER OFFSET — HOLDMEMBRANE RETURN DEPTH INTO REVEALS — HOLDCOVER-PATCH EXTENSION PAST A CUT — HOLDMEMBRANE UV EXPOSURE LIMIT — HOLDWHOLE-ASSEMBLY AIR-LEAKAGE TARGET — HOLDBASE, OPENING + CORNER VALUES — SEE INSETS NOTES — VERBATIMNOTE 1 — GOVERNANCEProject drawings, specifications, approved submittals, manufacturer instructions and applicable codes govern. The FPG Detail Library is a controlled reference and generation resource and does not replace project-specific design or approval.NOTE 2 — SCOPE RESPONSIBILITYScope responsibility varies by project — coordinate with the approved responsibility matrix.NOTE 3 — FASTENERSFasteners shown are illustrative only. Type, material, spacing, embedment, edge distance and structural capacity must follow the approved project design and manufacturer requirements.

Transcript — the installation sequence in words

The animation is muted and carries no audio track. This is its complete text equivalent: one entry per step, in build order, matching the on-screen captions.

  1. Step 01 — SUBSTRATE. The bonding substrate: exterior sheathing over a steel stud frame, with the window rough opening already cut and a pipe penetration stubbed through — everything the barrier must seal to is in place before any membrane is opened.
  2. Step 02 — SURFACE PREP + PRIMER. Sheathing is checked clean, dry, sound and dust-free, then primed where the membrane manufacturer requires it — adhesion is the whole attachment method for this system, so the surface is the first thing that can fail it.
  3. Step 03 — JOINT TREATMENT + CORNER PRE-STRIPS. Sheathing joints, fastener lines and both corner types are detailed before any field sheet goes on, so the field membrane never has to bridge an open gap and every later field lap sheds over — never behind — the reinforcement.
  4. Step 04 — BASE TIE-IN. The barrier is landed on the base through-wall flashing first: the transition membrane bonds to the sheathing and laps down over the flashing upstand, so water on the membrane is handed outward onto the metal and out past the drip, never behind it.
  5. Step 05 — FIRST COURSE. The lowest self-adhered sheet is set first, lapping down over the base transition strip; the release liner is peeled progressively as the sheet is positioned and the sheet is rolled as it lands — an unrolled sheet is not yet installed.
  6. Step 06 — COURSING UP TO THE PENETRATION. Courses work strictly bottom-up so every horizontal lap sheds like a shingle and vertical end laps are staggered course to course; coursing is stopped deliberately at the pipe rather than running past it.
  7. Step 07 — PENETRATION COLLAR — INTERLEAVED. The pipe collar is installed while the coursing is still open at that level, not after the wall is covered: the collar bonds to the pipe and fans onto the membrane below and beside it, then the next course up laps over the collar’s upper flange so the counter-lap is real and nothing has to be peeled back.
  8. Step 08 — COURSING HELD AT THE HEAD LINE. Coursing continues up past the sill and alongside the opening, returning into the jamb reveals — then stops one course short of the window head, because the opening must be detailed before anything covers the head.
  9. Step 09 — SILL PAN. The rough-opening sill gets a membrane pan with a continuous back dam and upturned ends, its apron lapped down over the field membrane already on the wall below — so anything that reaches the sill is delivered out of the opening, not into the wall.
  10. Step 10 — JAMBS, HEAD, THEN THE CLOSING COURSE. Jamb strips lap over the sill-pan end upturns; the head strip goes on last, over both jambs; only then does the held field course above the opening lap down over the head strip — pan, jamb, head, field, each layer outboard over the one it drains onto. Scope responsibility varies by project — coordinate with the approved responsibility matrix.
  11. Step 11 — TOP TERMINATION + FULL ROLLER PASS. The top edge of the barrier is mechanically terminated and sealed rather than left to rely on adhesion alone, and the whole plane gets a final pressure pass — fishmouths, wrinkles and unbonded edges are cut, laid flat and patched, never left to be covered by cladding.
  12. Step 12 — FLUID-APPLIED ALTERNATE. Alternate method for the same airtightness line: a fluid-applied membrane built to the manufacturer’s specified wet-film thickness, with detail fabric embedded at joints, corners, penetrations and transitions before the monolithic field coat — the sequence logic is unchanged, only the material form.
  13. Step 13 — CONTINUITY — THE AIRTIGHTNESS LINE. One unbroken line traces the completed air barrier — base flashing tie-in, field, both corners, the penetration collar and the full opening perimeter — because an air barrier only performs as a continuous plane; drops then run the drainage path and every one exits outward.
  14. Step 14 — COMPLETE ASSEMBLY. Finished barrier — NTS, illustrative. Callouts: head, jamb, sill pan, base tie-in, penetration, top termination, inside corner, outside corner; the completed plane becomes the inboard, airtight face of the future drained and ventilated rainscreen cavity.

What is on HOLD, and why

The FPG Detail Library seed holds cladding trim and sheet-metal flashing profiles only. It contains no record for air and water-resistive barrier membranes, so no dimension in this drawing is backed by a library record and none is shown. Every quantity below is drawn on the diagram as a visible HOLD chip and is recorded in the embedded machine-readable provenance.

Held quantities

  • HOLDSteel stud spacing and sheathing thickness (context geometry)
  • HOLDRough-opening size and pipe penetration diameter
  • HOLDMembrane sheet width / course height
  • HOLDHorizontal lap width (sheet courses)
  • HOLDVertical / end lap width and stagger offset
  • HOLDPrimer coverage rate and open/flash time
  • HOLDMinimum and maximum substrate / ambient application temperature
  • HOLDSheathing joint-strip width
  • HOLDCorner pre-strip width / leg length (inside and outside)
  • HOLDBase transition membrane lap onto flashing upstand
  • HOLDThrough-wall flashing profile geometry, upstand height, slope, drip projection and end-dam height
  • HOLDBase flashing height above finished grade / floor
  • HOLDFlashing length-to-length lap dimension
  • HOLDMembrane return depth into rough-opening reveals
  • HOLDFluid-applied wet-film / dry-film thickness, number of coats and recoat/cure time
  • HOLDDetail-fabric embedment width at joints, corners, penetrations and transitions (fluid alternate)
  • HOLDPenetration collar overlap onto field membrane (and onto the pipe)
  • HOLDSealant fillet size at penetration and at termination bar
  • HOLDSill pan back dam height
  • HOLDSill pan end-upturn height
  • HOLDSill pan slope to exterior
  • HOLDJamb/head strip return width onto field
  • HOLDCover-patch extension past a cut fishmouth
  • HOLDTop termination height and termination-bar fastener type, material, spacing, embedment and edge distance (Note 3)
  • HOLDMembrane exposure limit before cladding (UV exposure duration)
  • HOLDMembrane vapour permeance / class (project design decision, Note 5)
  • HOLDAir-leakage rate / whole-assembly airtightness target (project design decision)

Governing notes

Project drawings, specifications, approved submittals, manufacturer instructions and applicable codes govern. The FPG Detail Library is a controlled reference and generation resource and does not replace project-specific design or approval.

Scope responsibility varies by project — coordinate with the approved responsibility matrix.

Fasteners shown are illustrative only. Type, material, spacing, embedment, edge distance and structural capacity must follow the approved project design and manufacturer requirements.