Rainscreen Cladding

Backing, continuity and cladding interfaces coordinated as one project-specific sequence.

01 / 04

Backing

Start with the backing and the specified project references.

02 / 04

Continuity

Coordinate barrier continuity against the selected system details.

03 / 04

Coordination

Review insulation, support and cavity coordination together.

04 / 04

Cladding

Bring cladding and transition references together for review.

Read the sequence and scope
  1. Backing. Start with the backing and the specified project references.
  2. Continuity. Coordinate barrier continuity against the selected system details.
  3. Coordination. Review insulation, support and cavity coordination together.
  4. Cladding. Bring cladding and transition references together for review.

Presentation only. Follow the specified project documents, selected system requirements and agreed review responsibilities. The reference geometry is illustrative and not to scale. Existing service limitations and technical notes remain below.

Further service context and original reference images
BUILDING ENVELOPE · RAINSCREEN

Pressure-equalized rainscreen assemblies engineered for the BC climate — ACM, phenolic, fibre cement, terracotta, corrugated metal.

Rainscreen Cladding
SYSTEMS
6 product lines
SUB-FRAME
Thermal-broken Al
INSULATION
Continuous mineral wool
STANDARD
NBC 9.27 / 5.6

Scope

How we build it

Every assembly engineered as a system: substrate, AVB, insulation, carrier, finish and closeouts — coordinated end-to-end.

  • Cassette + plank panel systems in 6 materials
  • Thermal-broken aluminum sub-framing (Cascadia FRP clips)
  • Continuous mineral wool insulation, taped joints
  • Self-adhered or fluid-applied air + vapour barrier
  • Pre-coordinated with windows, parapets, base and soffit details

Need an envelope priced + installed?

Send drawings + spec section — we return a budgetary number within 5 business days.

Project-specific reference details and governing notes
Rainscreen cavity and drainage — generic drained and ventilated wall assembly, cabinet-oblique sequenceCabinet-oblique cutaway of a generic rainscreen wall: framing and sheathing, water-resistive barrier as the drainage plane with shingle laps, base flashing with a hemmed drip, vertical furring forming the cavity, head and sill flashings at a window opening, a floor-line cavity flashing dividing the cavity with a screened exhaust below and a screened intake above, continuous vertical compartment baffles at the inside and outside corner lines, insect-screened vents, a generic cladding plane with open joints, traced water paths that always exit outward, airflow chevrons for each compartment, and seven detail insets — base, floor line, head, sill, jamb plan, top vent, and true outside- and inside-corner plans. Not to scale, illustrative; every dimension is held. RAINSCREEN CAVITY AND DRAINAGE — ASSEMBLY SEQUENCEFig Philp Group Inc. · Motion V1 · cabinet-oblique assembly — NTS, illustrative · generic system, cladding-agnosticLAYER SEQUENCE 01 SUBSTRATE — SHEATHING ON FRAMINGROUGH OPENING PRE-CUT · JOINTS DASHED LAPCOURSE LOOSEWINDOW SCOPE:SEE NOTE 202 DRAINAGE PLANE (W-R BARRIER)SHINGLE LAPS SHED DOWN AND OUTPAN UNDER · JAMBS OVER · HEAD OVER JAMBS DRIP KICK — CLEAR OF WALLHOLDS — NOTHING HERE IS DIMENSIONEDFLASHING SLOPES + END DAMS: HOLD (N4)03 BASE FLASHING + DRIPBACK LEG BEHIND THE BARRIER LAPHEM CLOSED DRY SIDE · ENDS TURNED UP THROUGH BARRIER INTO STRUCTURECAVITY DEPTH — NO VALUE SHOWN (NOTE 1)CAVITY DEPTH: NTS — HOLD (NOTE 1)FURRING STANDOFF: NTS — HOLD (N4)FASTENERS: NTS — HOLD (NOTE 3)04 FURRING — THE CAVITY IS BORNFASTENERS ILLUSTRATIVE — NOTE 3HELD CLEAR OF EVERY FLASHING SHELF 05 OPENING FLASHINGSEND DAMS RUN PAST THE JAMB LINES BAFFLE (IC LINE)BAFFLE (OC LINE)COMPARTMENT LAYOUT: HOLD (N4/N5)06 COMPARTMENTALIZATIONDIVIDERS DRAIN AND VENT — NOTE 5 TOP EXHAUSTINTAKE ABOVEEXHAUST BELOWBASE INTAKEVENT + SCREEN OPEN AREA: HOLD (N4)07 INSECT SCREENS + VENTSSHELF INTO CAVITY · UPSTAND BEHIND CLADDING CLADDING — ANY SYSTEM, PER PROJECT SPEC — NTSOPEN JOINTS — THE SKIN IS ALLOWED TO LEAKCLEARANCE GAPOPEN JOINT + CLEARANCE GAP: HOLD (N4)08 CLADDING — ANY SYSTEMFASTENING ILLUSTRATIVE — NOTE 3OPEN JOINTS · CLEARANCE AT EVERY FLASHING DEFLECTION — MOST RAIN SHEDS AT THE CLADDING FACE09 DEFLECTION — THE FIRST DMOST RAIN NEVER REACHES A JOINT CAPILLARY BREAK (ZOOM, NTS)WATER ENTERS AN OPEN JOINTAND MEETS THE CAVITYGAP TOO WIDE TO BRIDGE — NTSFILM CLINGS TO THE CLADDING BACKAND FALLS INSIDE THE CAVITYWIDTH: NTS — HOLD (N1)10 CAPILLARY BREAKGAP TOO WIDE TO BRIDGE — SEE ZOOM DRAINAGE — EVERY PATH EXITS OUTWARD, NONE DEAD-ENDS11 DRAINAGE — THE SECOND DEVERY PATH EXITS OUTWARD DRYING — MOVING AIRCARRIES RESIDUALMOISTURE OUTPRESSURE MODERATIONVENTILATION — EACH COMPARTMENT: LOW INTAKE, HIGH EXHAUST12 VENTILATION + DRYINGSTACK EFFECT + WIND — NO RATES SHOWN 13 DETAIL CALLOUTS + INSETSHEADHEAD — FLASHING, END DAMS, SLOTJAMBJAMB — SCREENED CAVITY RETURNSILLSILL — PAN + SLOPED FLASHINGBASEBASE — INTAKE, DRIP, CLEARANCEFLOORFLOOR LINE — COMPARTMENT FLASHINGICINSIDE CORNER — PLAN INSETOCOUTSIDE CORNER — PLAN INSETTOP VENT — EXHAUST + SCREEN INSETBASE (SECTION, NTS)CLADDING TERMINATES CLEARSCREEN BEHIND CLADDING PLANEHEM CLOSED — NO WATER POCKETBACK LEG BEHIND BARRIER LAPINTAKE AIRGAPS + SLOPE: HOLD (N4)FLOOR LINE (SECTION, NTS)SCREENED INTAKE ABOVE SHELFSCREENED EXHAUST BELOW FACEEND DAM (BEYOND, DASHED)DRIP CLEAR OF CLADDING BELOWA DIVIDER THAT DRAINS AND VENTSSLOPE + OPENINGS: HOLD (N4)HEAD (SECTION, NTS)CAVITY CONTINUES ABOVESCREENED DRAINAGE / INTAKE SLOTEND DAM PAST THE JAMB LINEHEM — SHEDS TO THE CLADDING FACEFURRING HELD CLEAR OF THE SHELFSLOPE + END DAMS: HOLD (N4)SILL (SECTION, NTS)PAN: UPTURNED BACK AND ENDSSLOPED SILL FLASHINGHEMMED DRIP KICK · ENDS TURNED UPSHEDS ONTO THE CLADDING FACESLOPE + DRIP: HOLD (N4)JAMB (PLAN, NTS)SCREENED CLOSURE AT THE REVEALCAVITY RETURNS AND DRAINS DOWN THE JAMBWINDOW — NOTE 2JAMB STRIP OVER PANRETURN: HOLD (N4)TOP VENT (SECTION, NTS)PARAPET OR SOFFIT — GENERICSCREENED EXHAUST — MOUTH OPENCLADDING TOP EDGE STOPS CLEAREXHAUST PATH LEFT CLEARHEIGHT + POSITION: HOLD (N4)OUTSIDE CORNER (PLAN, NTS)CONTINUOUS BAFFLEFRAMINGSHEATHINGBARRIERCAVITYFURRINGCLADDINGLAYER STACK TURNS THE ARRIS — CONTINUOUS — NTSBAFFLE NEEDS NO SLOTS — FLOW PASSES VERTICALLY BESIDE IT — NTSINSIDE CORNER (PLAN, NTS)CONTINUOUS BAFFLEFRAMINGSHEATHINGBARRIERCAVITYFURRINGCLADDINGLAYER STACK TURNS THE RE-ENTRANT CORNER — CONTINUOUS — NTSBAFFLE NEEDS NO SLOTS — FLOW PASSES VERTICALLY BESIDE IT — NTSNOTES — VERBATIM1. Cavity depth is governed by the applicable building code and the approved project design — jurisdiction-specific, shown NTS, HOLD. Verify project drawings, approved shop drawings and the governing code before construction.2. Scope responsibility varies by project — coordinate with the approved responsibility matrix.3. Fasteners shown are illustrative only. Type, material, spacing, embedment, edge distance and structural capacity must follow the approved project design and manufacturer requirements.4. Flashing slopes, projections, upstand, end-dam and end-lap dimensions, vent and slot open areas, screen perforation sizes, cladding open-joint widths, clearance gaps, furring standoff at flashings, and compartment layout and spacing are project-specific — NTS, HOLD. Verify project drawings, approved submittals and manufacturer requirements.5. Whether the cavity is compartmented, and the extent of any compartments, is set by the approved project design; compartment dividers are drawn here as drained and vented conditions, never as sealed dams.GOVERNANCE. Project drawings, specifications, approved submittals, manufacturer instructions and applicable codes govern. The FPG Detail Library is a controlled reference and generation resource and does not replace project-specific design or approval.

Transcript — the rainscreen cavity sequence in words

A complete text equivalent of the animation. Every step is listed with its caption and a description of what the drawing shows. Nothing here depends on JavaScript.

  1. Step 1 — Substrate. Exterior sheathing over the structural wall — every rainscreen begins with a continuous substrate that the drainage plane can be applied to. Drawn: Cutaway reveals framing at the section edge; sheathing panels slide over it with joints dashed; a window rough opening is pre-cut in the field. No dimensions — NTS.
  2. Step 2 — Drainage plane (W-R barrier). The water-resistive barrier is the drainage plane — lapped shingle-fashion so every seam sheds down and out, and returned into the rough opening with the sill pan under, jambs over, head over the jambs. Scope responsibility varies by project — coordinate with the approved responsibility matrix. Drawn: Dark W-R barrier covers the sheathing field; horizontal laps drawn dashed with an over/under tell at the cut edge; rough-opening membrane sequence animates in shingle order (sill pan with upturned back and ends, jamb strips lapping over the pan, head strip lapping over the jambs). The lowest field course and the courses at the base, floor line and window head are shown left loose (unbonded) where a flashing upstand will later be tucked behind them. Window unit set into the protected opening marked ‘WINDOW SCOPE: SEE NOTE 2’. Legend: ‘W-R BARRIER = DRAINAGE PLANE’.
  3. Step 3 — Base flashing + drip. At the wall base, a sloped flashing catches everything the drainage plane delivers — its back leg tucks behind the barrier shingle-fashion, its shelf slopes outward, and the hemmed drip edge kicks water clear of the wall below instead of letting it track back. Drawn: Base flashing profile installs across the wall base: the loose lower barrier course lifts, the back leg slides up behind it and the course re-laps down over the upstand (shingle order animated), outward-sloped shelf, down-turned face, hem folded closed on the dry side with no upturned water pocket; ends and any splices are shown turned up as dams rather than left open. A short arrow shows the drip kick trajectory clear of the wall. Slope, projection and end-lap treatment labelled ‘NTS — HOLD (NOTE 4)’.
  4. Step 4 — Furring — the cavity is born. Vertical furring strapped through the barrier to structure stands the future cladding off the wall — the space it creates is the rainscreen cavity, and its depth is set by the governing code and project design, not by this drawing. Drawn: Vertical furring members land in columns over the barrier, aligned to structure and interrupted at the opening and at the floor line where the compartment flashing will run through; each column stops short of the base-flashing shelf so drainage and intake air pass beneath it, and is held clear of the head-flashing shelf above the opening for the same reason. Fastener markers drawn at each attachment with a direction arrow through the barrier into structure, legend ‘FASTENERS ILLUSTRATIVE — NOTE 3’. The gap between barrier face and future cladding plane is dimension-flagged ‘CAVITY DEPTH: NTS — HOLD (NOTE 1)’ with an open dimension line carrying no number; the furring standoff at flashings is flagged ‘NTS — HOLD (NOTE 4)’.
  5. Step 5 — Opening flashings. The cavity must stay continuous around the window: a sloped head flashing tucked behind the barrier collects cavity water from above, holds it between upturned end dams that run past the jambs, and returns it outward — and a sloped sill flashing below the frame sheds onto the cladding face. Both hemmed, neither trapping water. Drawn: Above the opening: the loose barrier course lifts, the head-flashing back leg goes up behind it and the barrier re-laps over the upstand (shingle order animated); outward-sloped shelf, down face, closed hem, end dams upturned at both ends with the flashing running past each jamb line rather than stopping at the reveal; the furring above is held clear of the shelf. The gap between the flashing face and the cladding to come is flagged as the future drainage-and-intake slot for the cavity above (‘NTS — HOLD, NOTE 4’). Below the frame: sloped sill flashing with hemmed drip kick and its ends turned up at the jambs so run-off cannot track back into the cavity. Jamb closures cap the cavity at the reveals, drawn perforation-free here and screened in Step 7.
  6. Step 6 — Compartmentalization. Where the project design calls for a pressure-moderated cavity, closures divide it: continuous vertical baffles at the corners stop air short-circuiting sideways between two faces at different wind pressures, and at the floor line a sloped cavity flashing divides the cavity vertically — and because it divides it, it must also drain out and hand fresh air to the compartment above. Drawn: Continuous vertical baffle strips appear in the cavity at the inside and outside corner lines, spanning barrier face to cladding back — solid, because a vertical strip crosses neither the vertical drainage path nor the vertical airflow path, so it needs no slots to stay drainable. At the floor line, a sloped through-cavity flashing installs into the gap left in the furring columns and runs continuously across the wall, detailed exactly like the head flashing: back leg up behind the lifted barrier course, outward-sloped shelf, end dams upturned, down face with a closed hem whose drip projects clear of the cladding face below. A screened exhaust opening sits immediately under its face for the compartment below; a screened intake opening sits immediately above its shelf, restoring air for the compartment above and doubling as that compartment’s water exit. Plan-inset callout rings appear at both corners and a section-inset ring at the floor line. Compartment extent labelled ‘COMPARTMENT LAYOUT AND SPACING: PER PROJECT DESIGN — NTS, HOLD (NOTE 4)’.
  7. Step 7 — Insect screens + vents. The cavity breathes at the bottom and the top of every compartment — perforated insect screen closes each intake and exhaust without closing it to air or water, and screens the jamb closures too, so the openings stay open for airflow and drainage but shut to pests. Drawn: Perforated screen profiles install at every cavity opening: at the base above the base flashing and at the floor-line intake, each with its shelf into the cavity and its upstand directly behind the coming cladding plane, never beneath it; at the floor-line exhaust and the slot above the head flashing, screening the opening between flashing face and cladding edge without narrowing the drainage exit; at the top-of-wall exhaust, closing the cavity mouth beneath the parapet or soffit termination while leaving the exhaust path clear. Jamb closures from Step 5 are shown perforated on the same pass. Perforation size, net open area and screen standoff labelled ‘NTS — HOLD (NOTE 4)’.
  8. Step 8 — Cladding — any system. The cladding closes the field — drawn generically, because the rainscreen principle is the same whatever the skin: it terminates independently above each flashing with a clearance gap, and its joints are allowed to leak. Drawn: Generic cladding panels/planks fasten to the furring with open joints; fastener markers along furring lines, legend ‘FASTENING ILLUSTRATIVE — NOTE 3’; field label ‘CLADDING — ANY SYSTEM, PER PROJECT SPEC — NTS’. Edges stop with a visible clearance gap over the base flashing, over the floor-line flashing and over the head flashing, and the top edge of each cladding run stops below the floor-line flashing face leaving the screened exhaust gap open (‘GAP: NTS — HOLD (NOTE 4)’); no bearing on any flashing or screen. Open joint width flagged ‘NTS — HOLD (NOTE 4)’.
  9. Step 9 — Deflection — the first D. Deflection: the cladding face sheds the great majority of rain by geometry alone — drips, slopes, and overlaps throw water off before it ever reaches a joint. Drawn: Animated rain streaks strike the cladding face; most trace down the face and off the base drip trajectory. Deflection arrows at the face; a small remainder is highlighted approaching an open joint, setting up Step 10. Label: ‘DEFLECTION — FIRST LINE OF DEFENCE’.
  10. Step 10 — Capillary break. Water that enters a joint meets the cavity — an air gap too wide for capillary suction to bridge, so the film cannot be drawn across to the barrier; it clings to the back of the cladding and falls. Drawn: Zoom to an open joint in section: a water film animates through the joint, reaches the back face of the cladding, and the capillary path across the cavity is drawn, then struck through — ‘CAPILLARY BREAK: GAP TOO WIDE TO BRIDGE — NTS’. The droplet detaches and falls inside the cavity. Cavity width again flagged ‘HOLD (NOTE 1)’.
  11. Step 11 — Drainage — the second D. Drainage: anything that gets past the cladding runs down the drainage plane, over every shingle lap, and leaves at the first flashing it meets — the base flashing and its hemmed drip, the floor-line flashing between its end dams and out through its screened slot, the head flashing above the window doing the same. Never inward, and never past a divider without an exit. Drawn: Animated water drops trace dashed accent paths: (1) down the barrier field, across the laps, onto the base flashing shelf and off the drip clear of the wall; (2) a drop released in the upper compartment lands on the floor-line flashing shelf, is contained by its end dams, and exits over its drip through the screened slot — showing that a compartment divider is also a drainage exit; (3) cavity water above the window onto the head-flashing shelf, contained by the end dams, out through the screened slot; (4) window run-off over the sill flashing, past its upturned ends and off the kick. Every path exits outward; no path dead-ends at a closure.
  12. Step 12 — Ventilation + drying — the last two Ds. Ventilation: every compartment takes air in low and lets it out high, driven by stack effect and wind — and that moving air is what delivers drying, carrying residual moisture out of the cavity while the corner baffles keep the flow vertical instead of sideways. Drawn: Intake arrow at the screened base gap, rising chevrons in the lower compartment, exhaust arrow at the screened opening under the floor-line flashing; the flow restarts above it at the screened floor-line intake and rises to the screened top-of-wall exhaust — each compartment shown with its own low intake and high exhaust rather than one continuous column. A short chevron column above the window shows the head slot restoring intake for the cavity above the opening. Damp shading on the barrier and cladding back fades as chevrons pass — ‘DRYING’. At a corner baffle, a sideways arrow is blocked: ‘COMPARTMENT — PRESSURE MODERATION’. Arrows animate during play, hold static when done.
  13. Step 13 — Failure-tolerant by design. This is the honest story of a rainscreen: it assumes the cladding will leak and is built so that leakage doesn’t matter — deflect most, drain the rest, dry what remains, and keep every exit path open. Finished assembly — NTS, illustrative. Drawn: Complete assembly with seven labelled callout rings — HEAD, JAMB, SILL, BASE, FLOOR LINE, IC, OC — and insets: HEAD (section: flashing behind the barrier lap, end dams dashed, screened drainage/intake slot, cavity continuity above), JAMB (plan: cavity return, screened closure at the reveal), SILL (section: sloped flashing, upturned ends, hem kick), BASE (section: clearance gap, furring held clear of the shelf, screen behind cladding plane, no water pocket), FLOOR LINE (section: sloped cavity flashing with end dams, screened exhaust below and screened intake above, drip clear of the cladding below), OUTSIDE CORNER (plan: true arris return, full layer stack turning the corner, continuous baffle at the corner line), INSIDE CORNER (plan: re-entrant return, continuous stack, continuous baffle in the junction). ‘NOTES — VERBATIM’ box rendered in the drawing carrying Notes 1–5 and the governance sentence, all verbatim.

How a drained and ventilated rainscreen cavity works

Deflection

The cladding face sheds the great majority of rain by geometry alone — drips, slopes and overlaps throw water off before it ever reaches a joint.

Capillary break

Water that enters a joint meets the cavity: an air gap too wide for capillary suction to bridge, so the film cannot be drawn across to the barrier. It clings to the back of the cladding and falls. The gap width is jurisdiction-specific and project-specific — shown NTS, on HOLD.

Drainage

Whatever gets past the cladding runs down the drainage plane, over every shingle lap, and leaves at the first flashing it meets. Every flashing shown is a sloped, hemmed, end-dammed exit — never a dam. A compartment divider that cannot drain is a defect, so the floor-line divider is drawn as a sloped flashing with its own screened slot.

Ventilation and drying

Every compartment takes air in low and lets it out high, driven by stack effect and wind. That moving air is what delivers drying, carrying residual moisture out of the cavity. No flow rates and no open-area percentages are shown — both are held.

Compartmentalization

Where the project design calls for a pressure-moderated cavity, continuous vertical baffles at the corner lines stop air short-circuiting sideways between two faces at different wind pressures. A vertical baffle crosses neither the vertical drainage path nor the vertical airflow path, so it needs no slots.

Failure-tolerant by design

The honest story of a rainscreen is that it assumes the cladding will leak and is built so leakage does not matter: deflect most, drain the rest, dry what remains, and keep every exit path open.

Detail conditions drawn

Seven detail views are drawn alongside the assembly. Below 760px they become selectable stacked technical-detail views.

  • Full assembly
  • Base (intake, flashing, clearance gap)
  • Floor line (compartment flashing, exhaust below, intake above)
  • Top vent (exhaust + screen)
  • Head (flashing, end dams, drainage/intake slot)
  • Jamb (plan, screened cavity return)
  • Sill (pan + sloped flashing)
  • Inside corner (plan, continuous baffle)
  • Outside corner (plan, continuous baffle)

What is held, and why no dimension appears

No record in the FPG Detail Library profile seed applies to this system family, and no numeric dimension from any other page is reused here. Every quantity below is therefore shown NTS with a visible HOLD in the drawing.

  • Cavity depth (code minimum is jurisdiction-specific) — Note 1
  • Capillary-break gap width — Note 1
  • Furring spacing, member size, and standoff at flashing shelves — Note 3 / Note 4 / project design
  • All fastener type, spacing, embedment, edge distance — Note 3
  • Base flashing slope, projection, upstand height, end-dam height, end-lap length, drip kick geometry — Note 4
  • Head flashing slope, end-dam height, extension past the jamb lines, drainage/intake slot size above it — Note 4
  • Sill flashing slope, drip projection, upturned end height — Note 4
  • Floor-line cavity flashing slope, projection, upstand, end-dam height, drip clearance past the cladding below, and the size of its exhaust and intake openings — Note 4
  • Clearance gap between cladding edge and every flashing (base, floor line, head) — Note 4
  • Cladding open-joint width — Note 4
  • Vent net open area at base intake, floor-line exhaust and intake, head slot and top exhaust — Note 4
  • Insect screen perforation size, open-area ratio, and screen standoff behind the cladding plane — Note 4
  • Compartment layout, height and spacing (including floor-line interval) — Note 4 / Note 5
  • W-R barrier lap widths, rough-opening membrane lap widths, and sill-pan upturn and end-dam heights — project design
  • Material thicknesses (sheathing, barrier, furring, cladding, flashing gauge) — not depicted numerically; per project specification
  • Top-of-wall termination height and exhaust position under the parapet or soffit — Note 4
  • Airflow rates / stack-effect magnitude — described qualitatively only, never quantified

Governing notes (verbatim)

Project drawings, specifications, approved submittals, manufacturer instructions and applicable codes govern. The FPG Detail Library is a controlled reference and generation resource and does not replace project-specific design or approval.

  1. Note 1 — cavity depth. Cavity depth is governed by the applicable building code and the approved project design — jurisdiction-specific, shown NTS, HOLD. Verify project drawings, approved shop drawings and the governing code before construction.
  2. Note 2 — scope responsibility. Scope responsibility varies by project — coordinate with the approved responsibility matrix.
  3. Note 3 — fasteners. Fasteners shown are illustrative only. Type, material, spacing, embedment, edge distance and structural capacity must follow the approved project design and manufacturer requirements.
  4. Note 4 — flashing, vent and cavity geometry. Flashing slopes, projections, upstand, end-dam and end-lap dimensions, vent and slot open areas, screen perforation sizes, cladding open-joint widths, clearance gaps, furring standoff at flashings, and compartment layout and spacing are project-specific — NTS, HOLD. Verify project drawings, approved submittals and manufacturer requirements.
  5. Note 5 — compartmentalization applicability. Whether the cavity is compartmented, and the extent of any compartments, is set by the approved project design; compartment dividers are drawn here as drained and vented conditions, never as sealed dams.